Engineering, procurement, fabrication and installation of two steam boilers with a capacity of 250 ton/hr at the İskenderun Iron and Steel Works Company.
Business Line: Steam Plants
Re-tubing and repair of pressure and non pressure parts of 10F-105A Steam Boiler in Tupras Refinery in Izmit. This boiler was originally built in 1997 by GAMA and had suffered an extensive damage due to an accident on February 2006.
Turnkey EPC project for installation of two pressure HRSG behind GE LM6000 PC Sprint type Gas Turbine and by-pass stack at İzmit Electric Power Generation Plant.
Pressure and output of HRSG; HP: 55 bara/14,5 ton/hr.
The supply, installation and erection of HRSG and diverter system for the behind of a Frame 6 Turbine by exporting to free zone.
Modification of 2 existing HRSG, were erected by BWG in 1997, by adding a new HP two pressure level for steam generation.
Project is completed 45 days before the date on the contract.
2 pcs. package type boiler ve BOP systems supply and Ankara delivery, 2 supervisor and 2 welder 2 months site works.
Supply and installation of Enerjisa Adana Combined Cycle Power Plant auxiliary steam boilers and turn key basis supply belongs to these systems.
HRSG Boiler and Exhaust by pass system supply, commissioning and training for Owner’s personnel.
Modernization of existing plant system turnkey basis.
One ea. HRSG (behind Frame 6 gas turbine), one ea. FM-120/97 and FM-103/88 natural gas and oil fired boiler design, supply and construction and existing HRSG modification.