RADES-C COMBINED CYCLE POWER PLANT PROJECT

One of the critical milestrones of our RADES-C Combined Cycle Power Plant Project in Tunisia, the first steam admission to the steam turbine was carried out successfully on 22 December 2021, and the synchronization works were completed as of 31 December 2021. 

Carried out with the help of gas turbine in the power plant before the new year, electricity production is now more efficient due to the steam turbine which came into operation in the new year. The electrical and load tests, and tuning processes of the entire system along with the steam turbine of our project continue rapidly.

Our next step constitutes the most important milestone of the project, which is putting the power plant into commercial operation for combiye Cycle portion.

In addition to these updates, 7.25 million man-hours have been reached without 1,590 lost-day accidents as of January 1, 2022. As GAMA, we prioritize occupational safety and health.

Congratulations to all of our Rades project team on their success.