150 MW Kirikkale Diesel Power Plant, Turkey

150 MW Kirikkale Diesel Power Plant

Based on PPA, the project is a fully privately financed and constructed on turn-key basis with two significant phases:

  1. Construction of 150 MW (established capacity) combined cycle diesel power plant (consist of 13 each 11 MW engines and one 9.5 MW steam turbune & generator),
  2. Operation of the power plant for 5 years with 8,760 hr/year and 130 MW-100% availability.

EPC contract includes all basic & detailed design of the power plant, procurement of all power plant equipment, all civil, structural works, all mechanical erection works, installation of all electrical, instrumentation and control systems. The contract also includes commissioning, start-up works and training of client’s personnel.

Operation of the plant is also in the scope of GAMA.

Location Icon
Location

Kirikkale, Turkey

Client Icon
Client

Electricity Generation Co. Inc (Government)

Contractor Icon
Contractor

GAMA - Barmek JV

Duration Icon
Project Duration

12 Months (February 2001 - February 2002)