16.5 MW Cakirlar Run of River Hydroelectric Power Plant, Turkey

16.5 MW Cakirlar Run of River Hydroelectric Power Plant

GAMA Renewable Energy Systems Construction Co. (GAYES), a subsidiary of GAMA, executed the project as the enginering, procurement and construction contractor.

With the altitude of 1,400 m – 930 m, run of the river type hydroelectric power plant project has 2×8.25 MW pelton turbines. Electromechanical equipments are provided by VAtech – STE – Indar Consortium on a turn-key basis.

Power Plant is delivered to the Owner with fully operational condition. In addition, GAMA Renewable Energy Systems assisted & managed relations with public & state authorities for the permits and licences on behalf of the Owner/Investor during the construction period.

Location Icon
Location

Murgul, Artvin, Turkey

Client Icon
Client

Anadolu Elektrik Üretim A.Ş. (a subsidiary of GAMA Enerji)

Contractor Icon
Contractor

GAYES (GAMA Renewable Energy Systems Construction Co.)

Duration Icon
Project Duration

26 Months (May 2007 - August 2009)