3×210 MW KEMERKOY THERMAL POWER PLANT FLUE GAS DESULPHURISATION PLANT

3×210 MW Kemerkoy Thermal Power Plant Flue Gas Desulphurisation Plant

GAMA Industry performed turnkey construction of Flue Gas Desulphurisation Plant with wet limestone process for 3×210 MW Kemerköy Thermal Power Plant Units I, II & III, consisting of Limestone Handling, Absorbent Preparation, Scrubbing (with 3 ea. Scrubbers), Flue Gas, Gypsum Dewatering & Handling, Utility, Electrical and C&I Systems, including infrastructure and buildings.

Location Icon
Location
Kemerkoy, Mugla, Turkey
Client Icon
Client
Turkish Electric Generation and Transmission Corp. (TEAS)
Contractor Icon
Contractor
Consortium of Babcock and Wilcox (USA) and GAMA Industry Inc.
Duration Icon
Project Duration
54 Months (September 1998 - March 2003)