3×210 MW Kemerkoy Thermal Power Plant Flue Gas Desulphurisation Plant, Turkey

3×210 MW Kemerkoy Thermal Power Plant Flue Gas Desulphurisation Plant

GAMA Industry performed turnkey construction of Flue Gas Desulphurisation Plant with wet limestone process for 3×210 MW Kemerköy Thermal Power Plant Units I, II & III, consisting of Limestone Handling, Absorbent Preparation, Scrubbing (with 3 ea. Scrubbers), Flue Gas, Gypsum Dewatering & Handling, Utility, Electrical and C&I Systems, including infrastructure and buildings.

Location Icon
Location

Kemerkoy, Mugla, Turkey

Client Icon
Client

Turkish Electric Generation and Transmission Corp. (TEAS)

Contractor Icon
Contractor

Consortium of Babcock and Wilcox (USA) and GAMA Industry Inc.

Duration Icon
Project Duration

54 Months (September 1998 - March 2003)