LINEAR PART OF MAIN GAS PIPELINE “ANANIEV – IZMAIL”

Linear Part of Main Gas Pipeline “Ananiev – Izmail”

GAYES performed turnkey construction of 76 km long pipeline with 1,200 mm diameter, including 6 km long Danube river passage parallel to the existing line and connect to it.

Moreover, construction of transformer buildings, pig receiver and launcher units as well as electrical works and communication and automation systems works are executed.

Location Icon
Location
Frunzovka, Ukraine
Client Icon
Client
CJSC Gastransit
Contractor Icon
Contractor
GAYES - GAMA Renewable Energy Systems Construction Corp.
Duration Icon
Project Duration
12 Months (September 2002 - September 2003)
Price Icon
Project Amount
108.6 Million USD