Denis Coal Handling and Transport System
Design, supply and construction of a unique coal conveyor system, extending from Denis coal mines to Soma Power Plant was performed by GAMA in two phases. A 8,500 m long, single line, down hill belt conveyor system are constructed during the first phase whereas two 5,500 m long lines were installed during the second phase.
The conveyors have a capacity of 1,000 tons/hr each, a belt width of 1,000 mm and belt speed of 4.5 m/sec.
The Project was executed in technological partnership with KRUPP Industritechnik GmbH (Germany), a subcontractor to GAMA Industry.