HEREKE CEMENT PLANT

Hereke Cement Plant

Design, construction, manufacturing and complete mechanical and electrical erection of 1 ea. complete crushing unit, 1,500 t/hr capacity 1 ea. complete pre-homogenising unit; 50,000 ton storing, 1,800 t/hr stacking and 800 t/hr reclaiming capacity 1 ea.

Location Icon
Location
Hereke, Turkey
Client Icon
Client
Nuh Cement Industry Corp. (Turkey)
Contractor Icon
Contractor
GAMA Industry Inc.
Duration Icon
Project Duration
a) 14 Months (April 1991 - June 1992) b) 12 Months (January 1993 - December 1993) c) 23 Months (June 1993 - May 1995) d) 7 Months (May 1996 - December 1996) e) 7 Months (September 2002 - March 2003).