Petro Rabigh Polyethylene Plant, PC1 – PE Plants, Saudi Arabia

Petro Rabigh Polyethylene Plant, PC1 – PE Plants

GAMA performed civil construction, structural steel erection, equipment installation, pipe prefabrication and erection, painting and insulation works for the two reactor buildings, process buildings, extrusion building, powder & pellet silo structures & silos, infrastructure, transformer stations and the other auxiliary buildings of the two polyethylene plants which are EPPE (Easy Process Polyethylene) and LLDPE (Linear Low Density Polyethylene) having production capacity of 250,000 Ton and 350,000 Ton per year respectively.

This project is undertaken by GAMA Industry Arabia Ltd.

Location Icon
Location

Rabigh, Saudi Arabia

Client Icon
Client

Petro Rabigh - (Saudi Aramco & Sumitomo Chemical Eng. J.V. - K.S.A)

Contractor Icon
Contractor

Tecnimont Arabia Ltd. / Italy

Duration Icon
Project Duration

26 Months (May 2006 - July 2008)

Price Icon
Project Amount

100 Million USD

Man Hour Icon
Man-Hour

7 Million Man-Hours