RABIGH CEMENT PLANT EXPANSION

Rabigh Cement Plant Expansion

GAMA performed construction of a new clinker production line with a capacity of 7,000 tons/day starting from and including the new limestone crusher up to and including the packing and bulk loading plant as well as construction work for new power plant and connection to existing lines.

Location Icon
Location
Rabigh, Saudi Arabia
Client Icon
Client
Arabian Cement Company
Contractor Icon
Contractor
GAMA
Duration Icon
Project Duration
35 Months (November 2005 - October 2008)
Price Icon
Project Amount
137 Million USD
Man Hour Icon
Man-Hour
6 Million Man-Hours