3×600 MW Shoaiba IWPP Phase-3
Mechanical erection of 3×600 MW boilers, 3 pcs. electrostatic filter, 1 pcs. ash handling system and 1 pcs. auxiliary boiler including paint touch-up works are implemented.
Mechanical erection of 3×600 MW boilers, 3 pcs. electrostatic filter, 1 pcs. ash handling system and 1 pcs. auxiliary boiler including paint touch-up works are implemented.
Shoaiba, Jeddah, Saudi Arabia
SWEC (Shoaiba Water and Electricity Company)
Siemens AG. / Ansaldo Caldaie. S.p.A
28 Months (December 2006 - March 2009)