3×600 MW Shoaiba IWPP Phase-3, Saudi Arabia

3×600 MW Shoaiba IWPP Phase-3

Mechanical erection of 3×600 MW boilers, 3 pcs. electrostatic filter, 1 pcs. ash handling system and 1 pcs. auxiliary boiler including paint touch-up works are implemented.

Location Icon
Location

Shoaiba, Jeddah, Saudi Arabia

Client Icon
Client

SWEC (Shoaiba Water and Electricity Company)

Contractor Icon
Contractor

Siemens AG. / Ansaldo Caldaie. S.p.A

Duration Icon
Project Duration

28 Months (December 2006 - March 2009)