Western Libya Gas Project – Wafa Coastal Plant, Libya

Western Libya Gas Project – Wafa Coastal Plant

GAMA Industry performed engineering, procurement and construction of 31 buildings with a total area of 28,600 square meters and execution of complete civil and mechanical installation works for the process, utility, underground and off-site areas of the WAFA Gas Plant.

Location Icon
Location

Mellitah, Libya

Client Icon
Client

AGIPGAS BV (Libya)

Contractor Icon
Contractor

JTS Contracting Comp.Ltd. (JGC - Japan, Technimont - Italy, Sofregaz - France)

Duration Icon
Project Duration

25 Months (May 2002 - June 2004)

Price Icon
Project Amount

208 Million USD (GAMA portion)

Man Hour Icon
Man-Hour

9 Million Man-Hours