Yamama Cement Plant – Line No.7, Saudi Arabia

Yamama Cement Plant – Line No.7

GAMA Industry performed turnkey construction of Yamama Cement Production Line No.7 with 10,000 tonnes/day clinker capacity at the existing cement plant facilities, within the scope of “Sales & Purchase Contract” and “Construction & Erection Contract”, including the construction of a new cement mill unit for the existing Line No.6 .

At the time, world’s biggest cement plant; Yamama Cement Plant is executed by GAMA Industry Arabia Ltd.

Location Icon
Location

Riyadh, Saudi Arabia

Client Icon
Client

YAMAMA Saudi Cement Plant

Contractor Icon
Contractor

GAMA Industry Arabia Ltd. & Polysius A.G. (Germany)

Duration Icon
Project Duration

34 Months + 9 Months (March 2004 - October 2007)

Price Icon
Project Amount

142 Million USD (GAMA portion)

Man Hour Icon
Man-Hour

8 Million Man-Hours