390 MW KAZANSKAYA COMBINED CYCLE POWER PLANT

390 MW Kazanskaya Combined Cycle Power Plant

EPC Contract for Modernization of 390 MW Kazanskaya CHPP-3 is implemented on a turnkey basis.

Modernization of Kazan CHPP-3 envisages delivery and installation of 1 piece of GE 9HA 01 gas turbine, 1 piece of GE H28.56 generator, 1 piece of CMI double-pressure HRSG.

EPC Contract’s scope covers procurement of all major equipment as well as other auxiliary equipment, and conceptual and detail engineering of the plant, civil and electro-mechanical installation works, test and commissioning works and training of the Employer’s staff.

Location Icon
Location
Kazan, Russian Federation
Client Icon
Client
TGK 16 (TAIF)
Contractor Icon
Contractor
GE and GAMA Power Systems (Closed Consortium Agreement)
Duration Icon
Project Duration
39 Months (May 2014 - July 2017)
Placeholder
Placeholder
Placeholder
Placeholder
Placeholder
Placeholder