Erdemir-Erenco Cogeneration Power Plant – HRSG Modification

Modification of 2 existing HRSG, were erected by BWG in 1997, by adding a new HP two pressure level for steam generation.

Project is completed 45 days before the date on the contract.

Location Icon
Location

Karadeniz Eregli, Turkey

Client Icon
Client

Erdemir – Erenco

Contractor Icon
Contractor

GAMA Power Systems Inc.

Duration Icon
Project Duration

18 Months (February 2004 - August 2005)