Construction and erection of 4×25 MW steam boilers and balance of plant.
GAMA constructed Units 1 & 2 as subcontractor to Babcock and Wilcox (U.S.A), and Units 3 & 4 under direct contract to the Cukurova Electricity Company.
Construction and erection of 4×25 MW steam boilers and balance of plant.
GAMA constructed Units 1 & 2 as subcontractor to Babcock and Wilcox (U.S.A), and Units 3 & 4 under direct contract to the Cukurova Electricity Company.
Erection of two 30 MW steam generators, 30 MW turbo generator and 20 MW turbo blower.
The Soma-B Power Plant consisting of six coal-fired production units and auxiliary systems, was constructed on a turn-key basis and in three stages as follows:
GAMA Industry executed complete erection and installation works and start-up and commissioning services for entire plant.
Flue gas desulphurization plant for 2×150 MW Cayirhan Thermal Power Plant Units I & II, consisting of 2 ea. 100 m high scrubbers, auxiliary systems and ancillary buildings.
GAMA Industry is responsible for detail design of all civil works, buildings, locally fabricated structural steel and equipment, complete electrical and instrumentation installation, and start-up and commissioning of the plant.
Turnkey construction of a single unit extension to the plant consisting of a lignite fired steam boiler and turbine-generator set (157 MW electric power capacity), Coal Handling System, Flue Gas Desulphurization Plant, Raw Water Supply System and Water Treatment Plant is implemented.
The Birecik Dam and Hydroelectric Power Plant is located on the Euphrates river in the South Eastern part of Turkey. Birecik Dam and Hydroelectric Power Plant is located on the Euphrates river in the South Eastern part of Turkey. Dam crest is more than 2.5 km. long and consist of earth embankment dams on the left and right banks of the river, having a concrete gravity dam section in between, which integrates the spillway and the intake structure to the powerhouse. The dam height is 62.5 m. Power house is equipped with six Francis turbines with 112 MW each, with a total capacity of 672 MW. An annual electricity production of about 2.5 billion kWh is anticipated. In addition, the 56 km2 reservoir is planned to be used for irrigation of 70,000 hectares of farmland. The project is implemented on a “finance-built-operate-transfer” bases, with an operation period of 15 years.
This is the first major project in Turkey to be implemented on finance-built-operate-transfer basis.
GAMA performed construction, manufacturing and erection of 478 MW Marmara Ereğlisi Natural Gas Combined Cycle Power Plant.
GAMA Industry performed turnkey construction of Flue Gas Desulphurisation Plant with wet limestone process for 3×210 MW Kemerköy Thermal Power Plant Units I, II & III, consisting of Limestone Handling, Absorbent Preparation, Scrubbing (with 3 ea. Scrubbers), Flue Gas, Gypsum Dewatering & Handling, Utility, Electrical and C&I Systems, including infrastructure and buildings.