4×25 MW MERSIN THERMAL POWER PLANT

4×25 MW Mersin Thermal Power Plant

Construction and erection of 4×25 MW steam boilers and balance of plant.

GAMA constructed Units 1 & 2 as subcontractor to Babcock and Wilcox (U.S.A), and Units 3 & 4 under direct contract to the Cukurova Electricity Company.

6×165 MW Soma-B Thermal Power Plant

The Soma-B Power Plant consisting of six coal-fired production units and auxiliary systems, was constructed on a turn-key basis and in three stages as follows:

  1. Stage: Construction of 2×165 MW Units 1 & 2
  2. Stage: Construction of 2×165 MW Units 3 & 4, including ash dam and hydraulic transport system
  3. Stage: Construction of 2×165 MW Units 5 & 6

2×150 MW Cayirhan TPP Flue Gas Desulphurization Plant

Flue gas desulphurization plant for 2×150 MW Cayirhan Thermal Power Plant Units I & II, consisting of 2 ea. 100 m high scrubbers, auxiliary systems and ancillary buildings.

GAMA Industry is responsible for detail design of all civil works, buildings, locally fabricated structural steel and equipment, complete electrical and instrumentation installation, and start-up and commissioning of the plant.

6×112 MW Birecik Hydroelectric Power Plant and Birecik Dam

The Birecik Dam and Hydroelectric Power Plant is located on the Euphrates river in the South Eastern part of Turkey. Birecik Dam and Hydroelectric Power Plant is located on the Euphrates river in the South Eastern part of Turkey. Dam crest is more than 2.5 km. long and consist of earth embankment dams on the left and right banks of the river, having a concrete gravity dam section in between, which integrates the spillway and the intake structure to the powerhouse. The dam height is 62.5 m. Power house is equipped with six Francis turbines with 112 MW each, with a total capacity of 672 MW. An annual electricity production of about 2.5 billion kWh is anticipated. In addition, the 56 km2 reservoir is planned to be used for irrigation of 70,000 hectares of farmland. The project is implemented on a “finance-built-operate-transfer” bases, with an operation period of 15 years.

This is the first major project in Turkey to be implemented on finance-built-operate-transfer basis.

3×210 MW Kemerkoy Thermal Power Plant Flue Gas Desulphurisation Plant

GAMA Industry performed turnkey construction of Flue Gas Desulphurisation Plant with wet limestone process for 3×210 MW Kemerköy Thermal Power Plant Units I, II & III, consisting of Limestone Handling, Absorbent Preparation, Scrubbing (with 3 ea. Scrubbers), Flue Gas, Gypsum Dewatering & Handling, Utility, Electrical and C&I Systems, including infrastructure and buildings.