ATYRAU REFINERY RECONSTRUCTION

Atyrau Refinery Reconstruction

Construction of additional units (gasoline, diesel, sulfur, hydrogen, coker) and renovation works for the Atyrau Refinery is implemented.

Civil construction works, structural steel works, mechanical works, piping works, electric and instrumentation works, insulation, painting and fire proofing works are performed by GATE (a subsidiary of GAMA with %50 share) as subcontractor to JGC.

Hereke Cement Plant

Design, construction, manufacturing and complete mechanical and electrical erection of 1 ea. complete crushing unit, 1,500 t/hr capacity 1 ea. complete pre-homogenising unit; 50,000 ton storing, 1,800 t/hr stacking and 800 t/hr reclaiming capacity 1 ea.

TUPRAS Izmir Refinery – CCR and Isomerization Plants

The existing refinery is extended with two new units to increase the capacity for high-octane-fuel and to produce unleaded-fuel.

Besides CCR and Isomerization Units a new cooling tower, a flare unit, three storage tanks were supplied and connections of existing and new units are performed.

This turn-key project is executed by FWI (Italy) and GAMA Industry Consortium.

Turkmenbashi Refinery CCR Platformer Unit

750,000 ton/year Continuous Catalytic Platformer Unit is the first of a series of projects, within the Modernisation Program of the existing 50 years old Turkmenbashi Refinery, located in western Turkmenistan, on the Caspian Sea shores.

GAMA Industry executed the turnkey construction works of this unit as a consortium member together with Chiyoda Co. from Japan.

Sakhalin-II LNG Plant

Sakhalin-II LNG Plant offsite, utility, OET piping and steel erection works are implemented.

Bukhara Refinery

GAMA Industry performed turnkey construction of a grass root refinery with a capacity of 2,55 million tons/year, which processes the gas condensate from Kokdumalak fields in Bukhara region.

The main products are 76 and 93 octane unleaded gasoline, jet fuel, diesel, C4 Cut for gasoline blending, LPG, propane solvent and sulphur.