6×380 MW SHOAIBA THERMAL POWER PLANT (STAGE II – PHASE 1+2)

6×380 MW Shoaiba Thermal Power Plant (Stage II – Phase 1+2)

GAMA performed Mechanical Erection Works for the 6 fuel oil fired Boilers, Electrostatic Precipitators and Ash Disposal System of the (3+3) x 380 MW Shoaiba Power Plant Units 6 to 11.

Total Erection Weight is 49,572 tons for 6 Units.

Location Icon
Location
Shoaiba Jeddah, Saudi Arabia
Client Icon
Client
Sceco West of S. Arabia
Duration Icon
Project Duration
36 Months (August 2004 - August 2007)