3×400 MW Shoaiba Thermal Power Plant (Stage-3), Saudi Arabia

3×400 MW Shoaiba Thermal Power Plant (Stage-3)

GAMA performed mechanical erection of 3×400 MW boilers, 3 pcs. electrostatic filter, 3 pcs. ash handling system and tagging works.

Location Icon
Location

Shoaiba, Saudi Arabia

Client Icon
Client

SEC (Saudi Electricity Company)

Contractor Icon
Contractor

Alstom Power Inc. / Alstom Power EBN

Duration Icon
Project Duration

24 Months (June 2009 – June 2011)