CAUSTIC SODA PRILLING PLANT

Caustic Soda Prilling Plant

GAMA Industry performed turnkey construction of 50,000 tpa Caustic Soda Prilling Plant, including civil construction and electro-mechanical erection as well as structural steel fabrication, material supply for all civil construction works and for some electrical/instrumentation works.

5×367 MW Shoaiba Thermal Power Plant – Stage 1

Mechanical, electrical & instrumentation erection of works of boiler package (5 Units), mechanical erection works of turbine hall (5 units), mechanical erection works of BoP (Balance of Plant).

100 MW Lough-Ree Peat Fired Power Plant – Site Development, Civil Works & Mechanical Works

Ground improvement, infrastructure works and buildings construction of 100 MW peat powered power plant.

Project consists of all earthworks, underground piping services, concrete construction of all buildings on site. There are app. 10 main buildings construction and foundations for tanks, conveyors, ponds pump stations, Transformers etc. 10,500 m2 building footprint, 71,000 m2 site construction area, 230,000 m3 building volume, 56,000 m2 access roads. Two mechanical contracts signed, boiler erection and balance of plant respectively. Project consist of 3,500 t of lifting and 8,800 numbers of butt weld and 11,000 m seal welding for the boiler and 200 t of piping, 80 t of support erection, 70 Valves and equipment for the balance of plant contract which contains 13,000 numbers of butt weld. 3,800 m2 main building area, 57 m height.

Hadeed II Direct Reduction Plant

GAMA Industry performed mechanical erection, partial material supply and instrumentation of 1,240,000 tpy capacity Direct Reduction Plant based on 93% metallisation of DRI.

400 MW Tynagh Combined Cycle Power Plant

Tynagh Energy Limited has built Galway’s first power generation facility. The circa €300 million power plant is a modern state-of-the art facility using the latest in advanced engineering technology. It uses the cleanest available fuel, natural gas, which significantly reduces emissions of carbon dioxide. For the first time, Galway city and the region has a reliable and efficient source of power.

Approximately 30 years life-span power plant was built under a turnkey contract with a consortium of General Electric Company / General Electric International Inc. and GAMA Power Systems Inc. The gas turbine used is a GE 9FA design. F-class gas turbines were developed in the late 1980s and are considered commercially proven with a track record of high availability and reliability. The steam turbine is a GE A15 ‘HEAT’ (high efficiency advanced technology) model, with a GE 9A5 electrical generator. The designs of both the A15 steam turbine and the 9A5 electrical generator were developments from previous GE models that are fully proven technology. These are logical evolutions from previous models and incorporate GE’s comprehensive design process and field-testing facilities which are without doubt world-class.

Yamama Cement Plant – Line No.7

GAMA Industry performed turnkey construction of Yamama Cement Production Line No.7 with 10,000 tonnes/day clinker capacity at the existing cement plant facilities, within the scope of “Sales & Purchase Contract” and “Construction & Erection Contract”, including the construction of a new cement mill unit for the existing Line No.6 .

At the time, world’s biggest cement plant; Yamama Cement Plant is executed by GAMA Industry Arabia Ltd.

EPCC Cement Plant New Clinker Production Line

Construction of the 3,500 ton per day capacity New Clinker Production Line No.3, including raw material and meal preparation and storage, preheater and clinker production, clinker cooling, clinker storage, raw meal and clinker dedusting, heat recovery and transportation systems is implemented.

This project is executed by GAMA Industry Arabia Ltd.